Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
ASX:BAK
31 July 2026
13–15 Rheola Street
West Perth WA 6005
+61 8 9386 0855
www.barklyrareearths.com
QUARTERLY ACTIVITIES REPORT
June 2026
Barkly Rare Earths Limited (ASX:BAK) (‘Barkly’ or the ‘Company’) is pleased to provide its
quarterly activities report for the period ended 30 June 2026, during which the Company
mobilised its Phase 1 drilling programme and progressed metallurgical testwork.
Highlights
Barkly Project
Two Environmental Mining Licences granted during the quarter, with
corresponding Notices of Authority received to commence exploration
activities.
Mobilised for the Phase 1 drilling programme at the Barkly Project,
comprising 10,000 m of shallow drilling across approximately 400 drillholes.
Appointed RSC as resource programme manager, strengthening the
Company’s rare earth exploration and resource development capability.
Advanced metallurgical testwork to assess beneficiation and
hydrometallurgical pathways for Barkly rare earth mineralisation.
Post quarter end, drilling commenced and the first sample batch was
submitted to ALS Geochemistry in Brisbane for laboratory analysis.
Buntine Project
Advanced Buntine field activities ahead of the originally planned Q4 CY2026
schedule with reconnaissance mapping and rock-chip sampling.
Submitted samples to the laboratory to further assess polymetallic
prospectivity across a 9 km mineralised corridor.
Corporate
Presented at the RIU Gold Coast Investment Showcase, met institutional
and sophisticated investor audiences in Melbourne and Sydney, and
engaged with potential offtake partners.
Awarded up to A$100,000 in Northern Territory Government non-dilutive co-
funding for mineral characterisation and metallurgical testwork.
Awarded up to a further A$115,000 co-funding to support Phase 1 expansion
drilling at the Barkly Project.
Post quarter end, appointed Leeuwin Wealth Pty Ltd to support investor
engagement and capital markets strategy.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 2
BARKLY PROJECT
Project Background
The Company’s historical exploration at two of the prospects within the Barkly Project includes
755 m of drilling in 46 shallow holes (Figure 1). The drillholes average ~16 m depth and cover
under 1% of the project area.
These drilling data were used to delineate an Inferred Mineral Resource of 40 Mt @ 2,100 ppm
TREO, including 710 ppmMREO,for 82,000tonnes of contained TREO, reported above a 430 ppm
NdPr cut-off grade (refer to Previous Disclosure statement set out on page 13 of this
announcement). The rare earth Inferred Mineral Resource is shallow, flat-lying, and open in all
directions laterally.
The initial 40-Mt rare earth Inferred Mineral Resource at Barkly is classified within two optimised
pit shells (green area in Figure 2). Drilling between the two resource areas indicates the potential
for lateral resource expansion in the intervening ~20 km, and more broadly across the Immediate
Zone (purple area in Figure 2).
Figure 1: Location of the Barkly and Buntine projects.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 3
The rare-earth-mineralised quartz sand at Barkly is interpreted to have been deposited on the
seabed in a marine palaeo-embayment encompassed by the Barkly Project tenements (Figure
2). This depositional setting provides the geological basis for the interpreted potential for
widespread grade and thickness continuity.
In part, the rare earth Inferred Mineral Resource is overlaid by a separate vanadium (V2O5)
Inferred MineralResourceof 200Mt @ 0.12%V2O5 for 240,000tonnes of contained V2O5,reported
above a 0.10% V2O5 cut-off grade and reported in accordance with the JORC Code (2012) (refer
to Previous Disclosure statement set out on page 13 of this announcement).
Figure 2: Extent of the initial Inferred Mineral Resource and the surrounding immediate, intermediate, and
extended zones of exploration interest targeted by the Company.
Grant of Environmental Mining Licences
Two Environmental Mining Licences (EMLs) were granted during the quarter, and the Company
received corresponding Notices of Authority to commence exploration activities from the
Minister for Mining and Energy (refer announcements released to the ASX on 28 April 2026 and
25 June 2026). These complement an existing Deemed Mining Licence (DML) held by the
Company.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 4
Drill Programme Mobilisation
Following one of the largest locally recorded wet seasons, which delayed field operations due to
ground conditions, the Company mobilised for its Phase 1 drilling programme at the Barkly
Project (Figure 3).
Figure 3: Unloading equipment and consumables at Calvert Hills Station for the Phase 1 drilling
programme.
The programme comprises a planned 10,000 m of shallow drilling across ~400 drillholes, with an
average depth of ~25 m each. The drilling plan is designed to:
a) target resource expansion across the Immediate Zone, coinciding with the Company’s
previously announced Exploration Target (refer to Previous Disclosure statement set out
on page 13 of this announcement);
b) target additional resource tonnes within the Intermediate Zone (yellow area in Figure 2,
above) after drilling reconnaissance holes. Based on indications of continuity from
existing data, the Company adopted a drilling grid of approximately 800 m × 800 m,
allowing cost-effective testing of new potential resource areas;
c) test for extensions of rare earth mineralisation beyond the Immediate Zone of exploration
interest, across the Intermediate Zone and more widely across the project area;
d) test for repetitive sequences of mineralisation below the current resource;
e) continue to build mineralisation knowledge; and
f) source samples to advance the metallurgical testwork.
The Board continuedto strengthen theteamofhighly experiencedtechnicaland commercial rare
earth industry experts, with the appointment of RSC as resource programme manager. RSC
brings extensive international experience in rare earth element exploration and resource
development, augmenting the Company’s technical capability.
To manage fuel availability risk and reduce cost, the Company contracted BP distributor,
Recharge Petroleum, to deliver bulk fuel required for civil works and drilling (Figure 4). The
Company’s 30,000 litre diesel tank was delivered to site to support the works crew and drill rig
operations.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 5
Figure 4: Bulk fuel being delivered at the Barkly Project.
The Company engaged two civil contractors (Figure 5) to prepare tracks and drill pads for the
drilling programme. The Company also contracted a multi-purpose drill rig from Colling
Exploration, an Indigenous-owned company based in Pine Creek, Northern Territory.
Figure 5: Front end loader used for preparation of drill pads and access tracks at the Barkly Project.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 6
Metallurgy
Auralia Metallurgy is undertaking an early-stage beneficiation testwork programme to assess
opportunities to upgradeBarkly mineralisation intoa rare earth mineralconcentrate. The ongoing
programme is evaluating flotation and complementary beneficiation techniques, with a focus on
concentrate grade, rare earth recovery and mass yield.
Specialised Metallurgical Services is managing a coordinated hydrometallurgical sighter
testwork programme conducted principally at Nagrom, with supporting work undertaken by
other specialist laboratories. The programme is evaluating potential rare earth extraction
pathways for Barkly mineralisation and resulting beneficiation products. A range of process
conditions is being assessed to establish preliminary extraction characteristics and identify the
most promising processing routes for further evaluation.
Together, these programmes form part of Barkly’s broader metallurgical development strategy.
The results and technical understanding generated through the mineralogical, beneficiation and
hydrometallurgical studies will be used to refine the scope and design of subsequent testwork
and focus future activities on the most prospective processing pathways.
The initial programmes are using pulp samples from the Company’s 2022 drilling programme.
Fresh samples generated from the 2026 Phase 1 resource drilling programme will be
progressively incorporated as they become available and will also provide material for more
advanced metallurgical testwork.
Post Quarter End
Following the end of the quarter, a third EML was granted to the Company by the Northern
Territory Department of Lands, Planning and Environment, complementing the two EMLs and
DML already held by the Company.
Drilling of the Company’s 10,000-m Phase 1 drilling programme commenced (Figure 6) after civil
works progressed sufficiently to provide access and prepare work areas.
Among the first holes to be drilled were several 60-m-deep holes situated near the two existing
optimisedpit shells that delineate the Inferred Mineral Resource. These deeper holes will provide
a stronger geological framework for understanding basin stratigraphy (Figure 7) and assessing
mineralisation continuity outside the existing resource.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 7
Figure 6: RC drilling at the Barkly Project.
Figure 7: Stratigraphic profile logging of drill chips sampled from a 60-m deep drillhole at the Barkly
Project.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 8
The early stage of the programme is focussed on establishing sample quality, optimising drilling
efficiency, and positioning the team for a steady ramp-up across the campaign (Figure 8).
Figure 8: (left) Barkly’s Managing Director, Craig Wright, and GM—Exploration, Richard Hall, discuss
the first drillhole setup; (right) Richard Hall discusses sampling with RSC technical personnel.
Samples are geologically logged at the rig, where two portable XRF (pXRF) instruments (Figure 9)
are used as qualitative field screening tools to assist geological logging and field planning. The
Company will rely on laboratory assays to determine rare earth grades.
Figure 9: pXRF chemical analysis during drilling at the Barkly Project.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 9
The first sample batch from the drilling programme was submitted to ALS Geochemistry in
Brisbane, an ISO/IEC 17025-accredited laboratory (Figure 10).
Figure 10: Barkly’s Managing Director, Craig Wright, meets with ALS Geochemistry sample preparation
manager, Shannon Holdsworth (left), and inspects laboratory sample preparation equipment (right).
BUNTINE PROJECT
Project Background
The Company previously identified three different anomalous zones of Pb-Co, U-W-Pb-Ni, and
Zn-Pb-Co-Cu along the mineralised corridor, with various historical rock chip samples grading
up to 667 ppm Zn, 1% Pb, 1,760 ppm Co, 316 ppm Cu, 10% Mn, 7,100 ppm Ni, and 239 ppm Cr
(refer to Previous Disclosure statement set out on page 13 of this announcement).
Field Work
The Company advanced exploration activities at its Buntine Base Metals Project (Figure 1),
originally planned for Q4 CY2026, by mobilising for reconnaissance mapping and rock-chip
sampling in June.
Samples were submitted to the laboratory in early July, with the aim of further assessing the
prospectivity for polymetallic mineralisation within outcropping Blue Hole and Campbell Springs
formations over a 9 km strike length.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 10
CORPORATE
Promotion
The Company presented at the RIU Gold Coast Investment Showcase in June and met
institutional and sophisticated investors during roadshows in Melbourne and Sydney. It also
engaged with potential future offtake partners.
The Company was represented at the Annual Geoscience Exploration Seminar (AGES) in Alice
Springs, where it engaged with government representatives and other stakeholders.
Non-Dilutive Grant Funding
The Company applied for, and was awarded, A$100,000 of grant funding under Round 19 of the
Northern Territory Government’s Geophysics and Drilling Collaborations Programme. The grant
supports a detailed campaign of mineral characterisation and testwork on a co-funded basis
within the Company’s ongoing metallurgical programme at the Barkly Project. The testwork is
intended to improve the Company’s understanding of rare earth mineralisation and provide
technical information to support future process development studies.
The Company was also successful in its application for Round 19 for up to a further A$115,000 in
non-dilutive co-funding to support expansion drilling at its 100%-owned Barkly Rare Earths
Project. It is expected to offset eligible exploration costs for the Phase 1 resource drilling
programme at Barkly, subject to the terms and conditions of the grant. The co-funded work will
comprise ~1,200 m of drilling across ~20 shallow stratigraphic control holes to a maximum depth
of 60 m.
The co-funded drilling is designed to examine untested areas beyondthe existing InferredMineral
Resource and generate geological data to inform future resource targeting across the 5,030 km2
Barkly Project. It will test the Company’s geological model of a regionally extensive, shallow,
sediment-hosted REE system developed within a palaeo-marine embayment of the Carpentaria
Basin. Results are expected to help define basin architecture, stratigraphic controls, facies
relationships, and the potential for deeper or repeated mineralised horizons, supporting more
focussed future exploration and resource growth targeting.
Cash
At 30 June 2026,theCompany held cash of A$5.42 million.Duringthe quarter the Companymade
payments to related parties of A$192,750, comprising non-executive directors’ fees and salary
payments to executive directors.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 11
Post Quarter End
The Company appointed Perth-based capital markets adviser, Leeuwin Wealth Pty Ltd, to assist
with investor engagement and capital markets strategy during an 18-month engagement.
The Company presented at the Northern Territory Investment Summit, where more than 100
business leaders, investors and key stakeholders gathered to connect, collaborate and support
growth across the region.
Other than the post-quarter events disclosed above, the Company is not aware of any additional
material corporate events after quarter end.
DISCLOSURE REQUIRED UNDER LISTING RULE 5.3.4
The Company was admitted to the Official List of the Australian Securities Exchange on 30
January 2026, having completed an initial public offering pursuant to a Prospectus dated 1
December 2025 and Supplementary Prospectus dated 8 January 2026. The quarter ended 30
June 2026 is covered by the Use of Funds statement contained in the Prospectus and the
Company provides the following information in compliance with Listing Rule 5.3.4.
Use of funds item
Prospectus
A$
Quarter
ended 30
June 2026
A$
Cumulative
amount
spent from
listing to end
of quarter
A$
Variance*
A$
Exploration at Barkly & Buntine
Projects
5,251,530 1,240,217 1,446,896 (3,804,634)^
Environmental baseline
development studies
25,000 0 0 (25,000)
Community engagement 50,000 5,426 5,426 (44,574)
Related party loans and settlements 203,026 0 205,631 2,605
Expenses of the public offer 1,127,050 0 821,200 (305,850)
Corporate and administration costs 1,093,393 125,703 401,685 (691,708)#
Working capital 688,911 133,570 133,570 (555,341)#
Total 8,438,910 1,504,916 3,014,408 (5,424,502)
* Material differences (>5% of forecast Use of Funds) are explained as follows:
^ The period between being admitted to the Official List of the ASX and the end of the quarter was
150 days. During this time only preparatory work in respect to exploration was carried out with
the Company anticipating a higher rate of expenditure in future quarters.
# The period between being admitted to the Official List of the ASX and the end of the quarter was
150 days, whereas the Use of Funds statement is forecasting expenditure for the subsequent 24-
month period. Accordingly, expenditure is significantly lower than forecast.
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 12
MINERAL TENEMENT HOLDINGS
Project Tenement Registered Holder Status Interest
Nature of
change
Barkly Project
NT
EL32452 Barkly Rare Earths Limited Granted 100% -
EL32453 Barkly Rare Earths Limited Granted 100% -
EL32454 Barkly Rare Earths Limited Granted 100% -
EL32455 Barkly Rare Earths Limited Granted 100% -
EL32456 Barkly Rare Earths Limited Granted 100% -
EL32473 Barkly Rare Earths Limited Granted 100% -
EL32474 Barkly Rare Earths Limited Granted 100% -
Buntine Project
NT
EL32529 Barkly Rare Earths Limited Granted 100% -
EL32530 Barkly Rare Earths Limited Granted 100% -
EL32531 Barkly Rare Earths Limited Granted 100% -
EL32532 Barkly Rare Earths Limited Granted 100% -
EL32534 Barkly Rare Earths Limited Granted 100% -
EL32535 Barkly Rare Earths Limited Granted 100% -
EL32586 Barkly Rare Earths Limited Granted 100% -
EL32587 Barkly Rare Earths Limited Granted 100% -
EL33162 Barkly Rare Earths Limited Granted 100% -
This announcement has been authorised for release by the Board of Barkly Rare Earths Limited.
ENDS
Enquiries
Barkly Rare Earths Investor Relations
+61 8 9386 0855
ir@barklyrareearths.com
About Barkly Rare Earths Limited:
Barkly Rare Earths Limited (ASX:BAK) is an Australian mineral exploration company focussed on the
discovery and development of economic mineral deposits, driven by technical expertise and disciplined
execution. Its strategy is to discover, delineate, and develop deposits capable of supporting long-term
production to meet growing global demand.
The Company’s flagship Barkly Project in Australia’s Northern Territory spans 5,030 km2
and is held 100%
by Barkly Rare Earths. It has an initial Inferred Mineral Resource of 40 Mt @ 710 ppm Magnet Rare Earth
Oxide (MREO), within 2,100 ppm Total Rare Earth Oxide (TREO) (reported above a 430 ppm NdPr cut-off
grade). The Mineral Resource includes a high terbium component, with low uranium and thorium. Initial
leaching tests achieved 74% MREO extraction, with initial beneficiation testwork returning a mineral
ASX ANNOUNCEMENT
QUARTERLYACTIVITIESREPORTJUNE2026
www.barklyrareearths.com 13
concentrate of 29,000 ppm TREO. The consistently high MREO grade and interpreted continuity of
mineralisation present an opportunity to build a project of global significance.
At the Company’s Buntine Project in the Northern Territory, the Fraynes Formation is
chronostratigraphically equivalent to the Barney Creek Formation that hosts the McArthur River Pb-Zn
deposit, making the Fraynes Formation a target for greenfields base metal exploration. Polymetallic
mineralisation is exposed at the Buntine Project along a 9 km strike length of late-Paleoproterozoic
sedimentary rocks and overlying Cenozoic sediments, with three different anomalous zones of Pb-Co, U-
W-Pb-Ni, and Zn-Pb-Co-Cu along the mineralised corridor. Rock chip samples grade up to 667 ppm Zn, 1%
Pb, 1,760 ppm Co, 316 ppm Cu, 10% Mn, 7,100 ppm Ni, and 239 ppm Cr.
For more information, please visit: https://barklyrareearths.com/link/yVdwGr.
Forward Looking Statements
This announcement includes various ‘forward-looking statements’ with respect to, among other things,
goals, plans, and strategies. Such forward-looking statements are not guarantees of future performance
and involve known and unknown risks, uncertainties and other factors beyond the control of the Company
that may cause the actual results, performance and outcomes to be materially different from those
expressed or implied by such statements. Forward-looking statements are provided as a general guide
only and should not be relied on as an indication or guarantee of future performance. Given these
uncertainties, recipients are cautioned not to place undue reliance on any forward-looking statement.
Subject to any continuing obligations under applicable law, the Company disclaims any obligation or
undertaking to disseminate any updates or revisions to any forward-looking statements in this
announcement to reflect any change in expectations in relation to any forward-looking statements or any
change in events, conditions or circumstances on which any such statement is based.
Previous Disclosure
The information in this announcement that relates to Exploration Targets, Exploration Results and Mineral
Resources is extracted from the previous report titled Barkly and Buntine Projects, Northern Territory,
Australia, Independent Technical Report, included as Annexure A to the Company’s Prospectus dated 1
December 2025. The previous report was prepared in accordance with the 2012 Edition of the JORC Code,
and it is available to view at the Company’s website www.barklyrareearths.com. The Company confirms
that it is not aware of any new information or data, as at the date of this announcement, that materially
affects the information included in the original market announcement and, in the case of estimates of
Mineral Resources, that all material assumptions and technical parameters underpinning the estimates in
the relevant market announcement continue to apply and have not materially changed. The Company
confirms that the form and context in which the Competent Person’s (Paul Teniere) findings are presented
have not been materially modified from the original market announcement.
Glossary
TREO (Total Rare Earth Oxide)
La2O3+CeO2+Pr6O11+Nd2O3+Sm2O3+Eu2O3+Gd2O3+Tb4O7+Dy2O3+Ho2O3+Er2O3+Tm2O3+Yb2O3+Lu2O3+Y2O3
NdPr (Neodymium-Praseodymium mixed oxide)
Nd2O3+Pr6O11
MREO (Magnet Rare Earth Oxide)
Nd2O3+Pr6O11+Tb4O7+Dy2O3
MREO Ratio (%)
MREO/TREO x 100
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
BARKLY RARE EARTHS LIMITED
ABN Quarter ended (“current quarter”)
86 641 565 139 JUNE 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date (6
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
(318) (524)
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (310) (485)
(e) administration and corporate costs (126) (402)
1.3 Dividends received (see note 3) - -
1.4 Interest received 10 10
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(744) (1,401)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements (409) (409)
(c) property, plant and equipment (28) (28)
(d) exploration & evaluation - -
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (6
months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities
(437) (437)
3. Cash flows from financing activities
- 8,000
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
- (821)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (provide details if material) - -
3.10 Net cash from / (used in) financing
activities
0 7,179
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
6,605 84
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(744) (1,401)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(437) (437)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
0 7,179
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (6
months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
5,425 5,425
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 5,387 6,605
5.2 Call deposits 37 -
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
5,425 6,605
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
193
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (743)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
-
8.3 Total relevant outgoings (item 8.1 + item 8.2) (743)
8.4 Cash and cash equivalents at quarter end (item 4.6) 5,425
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 5,425
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
7.3
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer:
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer:
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer:
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: 31 July 2026
Authorised by: By the Board
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from
Share your feedback
Discover