Barkly Rare Earths (ASX:BAK) (‘BAK’ or the ‘Company’) is pleased to provide an update to
exploration planning at the Company’s flagship Barkly Project.
HIGHLIGHTS
Environmental Mining Licence granted, and Notice of Authority received to commence
exploration activities.
Phase 1 resourceextension programme of>10,000 metres of drilling across ~400 shallow
holes, mobilising late-May, designed to test for potential expansion of the existing 40 Mt
Inferred Mineral Resource and test lateral continuity across the project area.
RC drilling complemented by sonic drilling to support future Indicated and Measured
Mineral Resources.
International mineral resource development specialist consultancy, RSC, appointed as
the resource programme manager.
Regional exploration at the Buntine Project brought forward, with reconnaissance
fieldwork scheduled for May and June.
PROGRESS SINCE HIGHLY SUCCESSFUL INITIAL PUBLIC OFFERING
Since closing the fully underwritten A$8 million IPO, which was oversubscribed, and listing on
the ASX in January 2026, the Company has continued planning and preparation for its RC and
sonic drill programme of over 10,000 metres. Notwithstanding inclement ground conditions and
disrupted fuel supply chains, the Company is on track to commence drilling in June, following
the grant this week of an Environmental Mining Licence and receipt of a Notice of Authority to
commence exploration activities from the Minister for Mining and Energy. This complements an
existing Deemed Mining Licence held by the Company.
The Board continues tostrengthen the team of highly experienced technical andcommercial rare
earth industry experts, with the appointment of RSC as resource programme manager. RSC
brings an extensive breadth of international experience in rare earth element exploration and
resource development, augmenting the already highly competent technical and commercial
skills across the Company’s management and Board team. RSC will initially supervise drilling at
Barkly under the direction of BAK’s executive team, providing a layer of quality assurance and
control in this first resource extension drilling programme.
ASX ANNOUNCEMENT
EXPLORATIONUPDATE
www.barklyrareearths.com 2
PHASE 1 DRILLING PROGRAMME
Phase 1 of the drilling programme encompasses over 10,000 metres of drilling across ~400
shallow holes, having an average depth of ~25 metres each. Mobilisation for drilling will occur
after the ground is sufficiently dry for the operation of heavy machinery and is currently planned
for late May 2026.
The programme targets expansion of the existing 40 Mt Inferred Mineral Resource, and is
designed to test lateral continuity across the project area. It will also evaluate sample quality and
bulk density data which the Company plans to use to support future resource upgrades.
Resource Growth — Immediate and Intermediate Zones
The established rare-earth-element Inferred Mineral Resource comprises 40 Mt @ 2,100 ppm
Total Rare Earth Oxide (TREO) for 82,000 tonnes of contained TREO, reported in accordance with
the JORC Code (2012) above a 430-ppm NdPr cut-off grade (refer to Previous Disclosure section).
The initial 40-Mt rare earth Inferred Mineral Resource at Barkly is classified within two optimised
pit shells (green area in Figure 1, below), and mineralisation is open in all directions laterally.
Drilling between the two resource areas suggests the potential for lateral resource expansion in
the intervening ~20 km, and more broadly across the Immediate Zone (purple area in Figure 1,
below).
Figure 1: Extent of the initial Inferred Mineral Resource and the surrounding immediate, intermediate, and
extended zones of exploration interest targeted by the Company.
ASX ANNOUNCEMENT
EXPLORATIONUPDATE
www.barklyrareearths.com 3
The Phase 1 drilling programme targets resource expansion across the Immediate Zone,
coinciding with the Company’s previously announced Exploration Target (refer to p.10 of the
Investor Presentation released to the ASX on 7 April 2026).
Based on indications of continuity from existing data, the Company has adopted a wide-spaced
drilling grid of approximately 800 m × 800 m, allowing cost-effective testing of new potential
resource areas.
The Company will use portable X-ray fluorescence (pXRF) instruments at the drilling rig to assess
the approximate grade of rare earth minerals in samples. The pXRF data collected each day will
inform the priority focus areas for the balance of Phase 1 drilling, supporting ongoing
optimisation of the programme as results are received. Using this approach, the Company also
aims to target additional resource tonnes within the Intermediate Zone (yellow area in Figure 1,
above) during Phase 1, after drilling reconnaissance holes.
Mineralisation Extension
The drilling programme will test for extensions of rare earth mineralisation beyond the Immediate
Zone of exploration interest, across the Intermediate Zone and more widely across the project
area.
The rare-earth-mineralised quartz sand at Barkly was deposited on the seabed in a marine
palaeo-embayment, which is encompassed by the Barkly Project tenements. Due to the nature
of seabed deposits, there is potential for widespread continuity of grade and thickness. The
stratigraphic package of host marine sediments extends across the Barkly Project area, and
conceptually, there are currently no identified geological constraints to extension beyond the
Immediate Zone, which will be tested through the Phase 1 programme.
Sample Type Evaluation
Most of the Phase 1 drilling programme is planned to be completed using an RC drilling rig. The
Company plans to complement this with a number of sonic-drilled twin holes to help evaluate
the quality of the RC samples. This will help the Company manage its drilling strategy for
improved resource definition during the planned eventual development of Indicated and
Measured Mineral Resources.
Additionally, the Company intends to use sonic drilling samples for bulk density measurements
to support the future development of Indicated and Measured Mineral Resources.
ASX ANNOUNCEMENT
EXPLORATIONUPDATE
www.barklyrareearths.com 4
BUNTINE EXPLORATION UPDATE
The Company is advancing exploration activities at its Buntine Base Metals Project (Figure 2,
below), originally planned for Q4 CY2026.
The reconnaissance mapping and rock-chip sample programme will be undertaken in May and
June, with the aim of further assessing the prospectivity for polymetallic mineralisation within
outcropping Blue Hole and Campbell Springs formations over a 9-km strike length.
The Company has identified three different anomalous zones of Pb-Co, U-W-Pb-Ni, and Zn-Pb-
Co-Cu along the mineralised corridor, with various historical rock chip samples grading up to 667
ppm Zn, 1% Pb, 1,760 ppm Co, 316 ppm Cu, 10% Mn, 7,100 ppm Ni, and 239 ppm Cr (refer to
BAK prospectus dated 1 December 2025).
Figure 2: Location of the Barkly and Buntine projects.
This announcement has been authorised for release by the Board of Barkly Rare Earths Limited.
Enquiries:
Barkly Rare Earths Investor Relations
+61 8 9386 0855
ir@barklyrareearths.com
ASX ANNOUNCEMENT
EXPLORATIONUPDATE
www.barklyrareearths.com 5
FORWARD LOOKING STATEMENTS
This announcement includes various ‘forward-looking statements’ with respect to, among other
things, goals, plans, and strategies. Such forward-looking statements are not guarantees of
future performance and involve known and unknown risks, uncertainties and other factors
beyond the control of the Company that may cause the actual results, performance and
outcomes to be materially different from those expressed or implied by such statements.
Forward-looking statements are provided as a general guide only, and should not be relied on as
an indication or guarantee of future performance. Given these uncertainties, recipients are
cautioned not to place undue reliance on any forward-looking statement. Subject to any
continuing obligations under applicable law, the Company disclaims any obligation or
undertaking to disseminate any updates or revisions to any forward-looking statements in this
announcement to reflect any change in expectations in relation to any forward-looking
statements or any change in events, conditions or circumstances on which any such statement
is based.
PREVIOUS DISCLOSURE
The information in this announcement that relates to Exploration Results and Mineral Resources
is extracted from the previous report titled Barkly and Buntine Projects, Northern Territory,
Australia, Independent Technical Report, as Annexure A to the Company’s Prospectus, of 1
December 2025. The previous report was prepared in accordance with the 2012 Edition of the
JORC Code, and it is available to view at the Company’s website www.barklyrareearths.com. The
Company confirms that it is not aware of any new information or data, as at the date of this
announcement, that materially affects the information included in the original market
announcement and, inthe case of estimates of Mineral Resources, that all materialassumptions
and technical parameters underpinning the estimates in the relevant market announcement
continue to apply and have not materially changed. The Company confirms that the form and
context in which the Competent Person’s (Paul Teniere) findings are presented have not been
materially modified from the original market announcement.
About Barkly Rare Earths Limited:
Barkly Rare Earths Limited (ASX:BAK) is an Australian mineral exploration company focussed on
the discovery and development of economic mineral deposits, driven by technical expertise, and
disciplined execution. Its strategy is to discover, delineate, and develop deposits capable of
supporting long-term production to meet growing global demand.
The Company’s flagship Barkly Project in Australia’s Northern Territory, has an initial Inferred
Mineral Resource of 40 Mt @ 710 ppm Magnet Rare Earth Oxide (MREO) within 2,100 ppm Total
Rare Earth Oxide (TREO) (reported above a 430-ppm NdPr cut-off grade). The Mineral Resource
includes a high terbium component, with low uranium and thorium. Initial sighter-level leach
tests achieved 74% MREO extraction, and sighter beneficiation test work delivered a mineral
concentrate of 29,000 ppm TREO. The consistently high magnet rare earth grade and continuity
ASX ANNOUNCEMENT
EXPLORATIONUPDATE
www.barklyrareearths.com 6
of mineralisation at the project, which spans 5,030 km2
and is held 100% by Barkly Rare Earths,
presents an opportunity to build a project of global significance.
At the Company’s Buntine Project in the Northern Territory, the Fraynes Formation is
chronostratigraphically equivalent to the Barney Creek Formation that hosts the McArthur River
Pb-Zn deposit, making the Fraynes Formation a target for greenfields base metal exploration.
Polymetallic mineralisation is exposed at the Buntine Project along a 9-km strike length of
Palaeoproterozoic sedimentary rocks and overlying Cenozoic sediments, with three different
anomalous zones of Pb-Co, U-W-Pb-Ni, and Zn-Pb-Co-Cu along the mineralised corridor. Rock
chip samples grade up to 667 ppm Zn, 1% Pb, 1,760 ppm Co, 316 ppm Cu, 10% Mn, 7,100 ppm
Ni, and 239 ppm Cr.