BARKLY READIES MAJOR 10,000 m RESOURCE
EXPANSION DRILLING PROGRAMME
Barkly Rare Earths Limited (ASX:BAK) (‘Barkly’ or the ‘Company’) is pleased to advise that civil
works are commencing this week to provide access and prepare work areas for its 10,000-metre
Phase 1 drilling programme, designed to test expansion potential around the existing 40 Mt @
2,100ppm TREOInferred rareearths Mineral Resource at theBarkly Project. Drilling is anticipated
to commence next week.
Highlights
• Full works crew mobilisation completed for 10,000 m ~400-hole Phase
1 drilling programme to commence next week
• Entire programme targets the expansion of the existing 40 Mt Resource
• Access tracks and pad preparation crew on site with works commencing
• 30,000 litre in-situ diesel tank delivered to support works crew and drill
rig operations
• Separately, Buntine Project samples have been submitted for assay,
with results expected Q3 CY2026
• Consistent investor update programme across Q3 and Q4, as Company
seeks to expand 40 Mt Inferred Mineral Resource by close Q4 CY2026
“This is an exciting step for Barkly. With site and pad preparation commencing
this week, we are readying our initial 10,000 m Phase 1 drilling programme aimed
at testing the next stage of growth from our existing 40 million tonne Inferred
Mineral Resource.
What makes Barkly’s ‘soft rock’ deposit particularly compelling is its
combination of substantial scale potential, mineralisation at surface, and low
deleterious radioactive element content, attributes that distinguish it from the
plethora of global ‘hard rock’ rare earths projects.”
Craig Wright — Managing Director
ASX ANNOUNCEMENT
BarklyReadies10,000mDrilling
www.barklyrareearths.com 2
BARKLY DRILLING PROGRAMME
Activity Update
The Company has assessed conditions at the Barkly Project and determined that the ground is
now dry enough to support the off-road heavy machinery required for clearing and drilling more
than 10,000 m across ~400 drillholes.
The Company’s 30,000 litre diesel tank was delivered to site, and earthmoving equipment for pad
and access preparation has arrived, including two loaders and one bulldozer. Work is scheduled
to commence in preparation for drilling planned for next week (Figure 1, below).
Figure 1: Site preparation and infrastructure for the 10,000 m Phase 1 drilling programme.
Phase 1 Drilling Plan
The drilling programme targets expansion of the existing 40 Mt Inferred Mineral Resource which
grades 2,100 ppm Total Rare Earth Oxide (TREO) for 82,000 tonnes of contained TREO. The
resource is reported in accordance with the JORC Code (2012) above a 430-ppm NdPr cut-off
grade (refer to Previous Disclosure section).
The initial 40-Mt Inferred Mineral Resource at Barkly is classified within two optimised pit shells
(green ovals in Figure 2, below), and mineralisation is open laterally in all directions. The
Company drilled four holes between the two resource areas that also intersected rare earth
mineralisation, suggesting potential for lateral resource expansion across the intervening
~20 km expanse and more broadlyacross theImmediateZone (purple area in Figure 2,below).
ASX ANNOUNCEMENT
BarklyReadies10,000mDrilling
www.barklyrareearths.com 3
The Company has designed the 10,000 m Phase 1 programme primarily comprising RC drilling to
target resourceexpansion across the Immediate Zone,coinciding with the Company’spreviously
announced Exploration Target (refer to ASX Announcement 7 April 2026i
). A majority of the ~400
shallow holes, averaging ~25 m deep, are planned within the Immediate Zone on an ~800 m
spacing.
Figure 2: Extent of the initial Inferred Mineral Resource and the surrounding Immediate, Intermediate, and
Extended zones.
The drilling programme will also test for extensions of rare earth mineralisation across the
Intermediate Zone (yellow area in Figure 2, above) and more widely across the project area. It will
also provide bulk density data and sample quality information, which the Company plans to use
to support future development of Indicated and Measured Mineral Resources.
The rare-earth-mineralised quartz sand at Barkly is interpreted to have been deposited on the
seabed in a marine palaeo-embayment encompassed by the Barkly Project tenements. This
depositional setting may support widespread continuity of grade and thickness. The extent of
mineralisation beyond the current Inferred Mineral Resource remains to be tested by drilling, and
this continuity will be determined through the Phase 1 drilling programme.
Drilling Technology
Two portable X-ray fluorescence (pXRF) instruments will be mobilised to site this week, which
will be used at the drilling rig by licensed operators to provide rapid indicative screening data
from samples. The pXRF data collected each day will inform the priority focus areas for the
balance of Phase 1 drilling, supporting ongoing optimisation of the programme as results are
analysed.
ASX ANNOUNCEMENT
BarklyReadies10,000mDrilling
www.barklyrareearths.com 4
Management incentives aligned with exploration success
The Company’s Executive has volunteered performance remuneration milestones that are
aligned with Mineral Resource growth and shareholder value development. These include lower
and upper milestones for Inferred Mineral Resource growth to 500Mt and 700 Mt,respectively,
at a minimum grade of 1,600 ppm TREO. Full details of the performance milestones are provided
in section 10.5 of the Company’s IPO Prospectus.
BUNTINE FIELD PROGRAMME
The Company has advanced exploration activities at its Buntine Base Metals Project (Figure 3,
below), originally planned for Q4 CY2026. The team undertaking reconnaissance mapping and
rock-chip sampling has completed its fieldwork and submitted samples for assay. The sampling
work was designed to further assess the prospectivity for polymetallic mineralisation over a 9-
km strike length.
The Company has identified three different anomalous zones of Pb-Co, U-W-Pb-Ni, and Zn-Pb-
Co-Cu along the mineralised corridor, with various historical rock chip samples grading up to 667
ppm Zn, 1% Pb, 1,760 ppm Co, 316 ppm Cu, 10% Mn, 7,100 ppm Ni, and 239 ppm Cr (refer to
BAK prospectus dated 1 December 2025).
Figure 3: Location of the Barkly and Buntine projects.
ASX ANNOUNCEMENT
BarklyReadies10,000mDrilling
www.barklyrareearths.com 5
CAPITAL MARKETS ADVISOR APPOINTED
The Company has appointed Perth-based capital markets adviser, Leeuwin Wealth Pty Ltd, to
assist with investor engagement and capital markets strategy. Consideration for the agreement,
which spans 18 months, is 6.0 million BAKO listed options (exercisable at A$0.30 and expiring 28
January 2029).
EXPLORATION NEXT STEPS
• Resource expansion drilling commencement (next week)
• Ongoing exploration results from 10,000 m of drilling in ~400 shallow holes (Q3 & Q4
CY2026)
• Rare earths concentration and extraction testing (ongoing)
• Mineral Resource estimate update (Q4 CY2026)
• Geo-metallurgical test work and modelling (Q3 & Q4 CY2026)
• Buntine exploration results (Q3 CY2026)
• Follow-up exploration at Buntine (Q4 CY2026)
This announcement has been authorised for release by the Board of Barkly Rare Earths Limited.
ENDS
Enquiries
Barkly Rare Earths Investor Relations
+61 8 9386 0855
ir@barklyrareearths.com
About Barkly Rare Earths Limited:
Barkly Rare Earths Limited (ASX:BAK) is an Australian mineral exploration company focussed on the
discovery and development of economic mineral deposits, driven by technical expertise and disciplined
execution. Its strategy is to discover, delineate, and develop deposits capable of supporting long-term
production to meet growing global demand.
The Company’s flagship Barkly Project in Australia’s Northern Territory spans 5,030 km2
and is held 100%
by Barkly Rare Earths. It has an initial Inferred Mineral Resource of 40 Mt @ 710 ppm Magnet Rare Earth
Oxide (MREO), within 2,100 ppm Total Rare Earth Oxide (TREO) (reported above a 430 ppm NdPr cut-off
grade). The Mineral Resource includes a high terbium component, with low uranium and thorium. Initial
conventional leaching tests achieved 74% MREO extraction, with initial beneficiation test work returning a
mineral concentrate of 29,000 ppm TREO. The consistently high magnet rare-earth grade and continuity of
mineralisation presents an opportunity to build a project of global significance.
ASX ANNOUNCEMENT
BarklyReadies10,000mDrilling
www.barklyrareearths.com 6
At the Company’s Buntine Project in the Northern Territory, the Fraynes Formation is
chronostratigraphically equivalent to the Barney Creek Formation that hosts the McArthur River Pb-Zn
deposit, making the Fraynes Formation a target for greenfields base metal exploration. Polymetallic
mineralisation is exposed at the Buntine Project along a nine-kilometre (9 km) strike length of late-
Paleoproterozoic sedimentary rocks and overlying Cenozoic sediments, with three different anomalous
zones of Pb-Co, U-W-Pb-Ni, and Zn-Pb-Co-Cu along the mineralised corridor. Rock chip samples grade up
to 667 ppm Zn, 1% Pb, 1,760 ppm Co, 316 ppm Cu, 10% Mn, 7,100 ppm Ni, and 239 ppm Cr.
For more information, please visit: barklyrareearths.com.
Forward Looking Statements
This announcement includes various ‘forward-looking statements’ with respect to, among other things,
goals, plans, and strategies. Such forward-looking statements are not guarantees of future performance
and involve known and unknown risks, uncertainties and other factors beyond the control of the Company
that may cause the actual results, performance and outcomes to be materially different from those
expressed or implied by such statements. Forward-looking statements are provided as a general guide
only and should not be relied on as an indication or guarantee of future performance. Given these
uncertainties, recipients are cautioned not to place undue reliance on any forward-looking statement.
Subject to any continuing obligations under applicable law, the Company disclaims any obligation or
undertaking to disseminate any updates or revisions to any forward-looking statements in this
announcement to reflect any change in expectations in relation to any forward-looking statements or any
change in events, conditions or circumstances on which any such statement is based.
Previous Disclosure
The information in this announcement that relates to Exploration Results and Mineral Resources is
extracted from the previous report titled Barkly and Buntine Projects, Northern Territory, Australia,
Independent Technical Report, as Annexure A to the Company’s Prospectus, of 1 December 2025. The
previous report was prepared in accordance with the 2012 Edition of the JORC Code, and it is available to
view at the Company’s website www.barklyrareearths.com. The Company confirms that it is not aware of
any new information or data, as at the date of this announcement, that materially affects the information
included in the original market announcement and, in the case of estimates of Mineral Resources, that all
material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The Company confirms that the form
and context in which the Competent Person’s (Paul Teniere) findings are presented have not been
materially modified from the original market announcement.
Glossary
TREO (Total Rare Earth Oxide)
La2O3+CeO2+Pr6O11+Nd2O3+Sm2O3+Eu2O3+Gd2O3+Tb4O7+Dy2O3+Ho2O3+Er2O3+Tm2O3+Yb2O3+Lu2O3+Y2O3
NdPr (Neodymium-Praseodymium mixed oxide)
Nd2O3+Pr6O11
MREO (Magnet Rare Earth Oxide)
Nd2O3+Pr6O11+Tb4O7+Dy2O3
MREO Ratio (%)
MREO/TREO x 100
i
ASX Announcement 7 April 2026 ‘Investor Presentation’. Apart from that which is disclosed in this
document, the Company, its directors, officers and agents are not aware of any new information that
materially affects the information contained in the 7 April 2026 announcement.
Share your feedback
Discover